Stage 2 – Build the Business Case
Detailed investigation involving primary research – both market and technical – leading to a Business Case, including product and project definition, project justification, and the proposed plan for development.
status: HOLD
A Gate 1 progress report has been posted in the project file outlining the findings to date and the recommendations.
In summary: The existing technology units would only break even at wholesale fuel prices and current NB retail electrical costs which provides little incentive to investors. More complex configurations would require components which may not exits yet.
planned start: 15/06/02 actual start:
planned finish: 15/09/01 actual finish: 15/05/31